Short news on NAS batteries

NGK’s NAS batteries are restarting

Existing NAS batteries systems are rebuilt by NGK Insulators Ltd. to reduce potential fire risk. Slowly, but surely, the fire incident of September 21, 2011, becomes a classified event.

xcel-energy-logoFor instance, Xcel Energy now announces it is restarting its battery plant that was commissioned in 2008 and stopped on NGK recommendation after the fire incident in Japan.

GE continues to massively hire storage experts

geThere are still ten open job positions related to Durathon on GE web site. There is even one in Japan for a Field Services Engineer, in the middle of NGK playground.

More than ever, a leading technology for grid applications

sodiumIn a recent article “Dynamic Modelling of Advanced Battery Energy Storage System for Grid-Tied AC Microgrid Applications“, researchers concludes:

“Sodium sulfur-type BESS devices are best suited to the requirements set by modern microgrid applications. These batteries can act in contingencies where rapid action is required to maintain the adequate levels of the grid frequency, but also in the case of high penetration of renewable generation, such as wind or solar photovoltaic, since the NaS battery can operate as the perfect complement in valley hours. In this case, the excess energy can be stored for delivery in peak hours. They are environmentally safe and have low maintenance while operate at high temperatures; it does not represent a major drawback. The biggest drawbacks are the cost and the limited information about these type of batteries which difficult the development of experimental prototypes and computer models. It is expected however that the appearance of other vendors reduces costs and facilitate the modelling.”

It is one of the numerous independent studies that recognise the advantages of NAS compared with other technologies for grid storage solutions.

Gauthier Dupont
Dupont Energy Consulting GmbH

Advertisements

GE and NGK spare no expense on molten salt batteries

Hustle and bustle in Schenectady, NY, USA

“GE Energy Storage is now open for business”, one can read in a recent General Electric video. The production commenced in September 2011. The Durathon™ battery factory officially opened on July 10, 2012, in Schenectady, NY. $100m were initially invested. Additional $70m are already committed to double the plant capacity.

It took three years at GE’s Global Research Center in Niskayuna, NY, to improve and perfect the technology bought in 2007 from Beta Research & Development, a UK company. And one years to build the plant.

Hundreds of new jobs were created. There are today 45 job offers on GE’s website. At full capacity, the factory will employ 450 workers and drive thousands of additional supply chain jobs throughout the region.

The first order was signed by Megatron Federal, a South African company, which will install 6,000 batteries in Nigeria to keep its telecom installations running during all too common power disruptions, decreasing its dependence on diesel backup generators, lowering fuel consumption and CO2 emissions.

Orders raise to $63m from about ten or so telecom customers.

Slow and steady in Nagoya, Japan

In his Fiscal Year 2012 2nd Quarter Results presentation, NGK Insulators Ltd. explains his strategy to reignite NAS batteries market:

  • Future trend:
    • Increasing overseas demand
  • Objectives:
    • To restore market confidence by implementing safety measures
    • To Expand sales of NAS batteries overseas and in renewable energy field
  • First steps:
    • Production priority put on safety measures
    • Resume production from November 2012
    • Overseas orders deferred to next year.

After the extraordinary FY11 (fiscal year from April 2010 to March 2011) losses of ¥4.8bn (€46m) related to NAS battery safety measures, sales of NAS batteries recovered at a slow pace in FY12 at ¥0.9bn (€9m) – see the figure opposite from NGK Insulators Ltd. But far beyond FY10 sales (¥19.7bn – €190m).

The deferment of order due to the priority put on safety measures is reflected in FY13 sales forecast that is as low as ¥0.2bn (€2m).

In NGK’s Summary of Consolidated Financial Results for the Six Months ended September 30, 2012, published on 31.10.2012, ¥38bn (€367m) are provisioned for NAS battery safety measures, down from ¥57bn (€552m) initially end of December 2011.

In nine months, 34% of the initial provision for NAS safety were invested. Taking into account NGK strategy explained above, one can expect that the remaining efforts would speed up, and that one year from now would be sufficient to completely solve safety issues. This assumption is in line with NGK announcement to defer overseas orders to next year.

The Hare and the Tortoise – Our Prediction

While GE is new in the race and try to force the pace, NGK, as usual, adopts an extremely cautious approach. Based on the moral of the tale, “slow and steady wins the race”, one could conclude that NGK is in best position.

But it would be too hastily, because GE and NGK are not (yet) playing in the same league:

  • NGK’ NAS batteries minimum size is one MW. The module are rated 50 kW, but they are not sold individually.
  • GE’s Durathon battery module delivers a few kW. Multiple Durathon modules can be connected in parallel if more capacity is needed. But they cannot be connected in series for higher voltage. MW range capacity then requires further developments.

They will then both win the race. Each on his own playground. NGK in large-scale grid applications, including integration with wind farms and large PV plants; and GE in medium-scale energy applications, like what they are doing in the telecom sector. But one day, both companies will meet in the same league. Then…

Gauthier Dupont
Dupont Energy Consulting GmbH

The first NAS batteries project after the fire incident of Sept. 2011

NGK resumes NAS batteries projects

In a previous post in last August, we have predicted that NGK Insulators‘ NAS batteries production shall resume in October 2012. The prediction is relatively correct: NGK has just announced the launch of its first implementation project since the fire incident that occurred on September 21, 2011.

Smart Grid Demonstration Project

1 MW of NAS batteries will be part of a Smart Grid demonstration project in Los Alamos, New Mexico. The information was simultaneously released on September 18th, 2012, by NGK Insulators and New Energy and Industrial Technology Development Organization (NEDO).

We have updated the list of NAS Battery Storage Systems accordingly.

The project aims to:

  • Expand the introduction of new energy
  • Promote energy conservation efforts and leading-edge technologies based on Japanese know-how, including large-scale stationary batteries for power grids and energy management systems
  • Contribute to international standardization activities for smart grid systems, which are steadily progressing on a global scale
  • Further promote the dissemination of Japanese smart grid technologies throughout the world.

The silver lining in the fire incident

Like for any incident, there are positive aspects afterwards.

Now, NAS batteries systems are safer. Not only thanks to a reinforced design, but especially because of the increased awareness of the real danger of such technology. They were neither an explosion, as many opponents predicted, nor toxic gas emissions, nor toxic liquid release. On an environmental point of view the fire incident proved that NAS batteries have a low impact.

“Only” a big fire, destroying the complete plant, but without any casualty. So the worst case is to lose the assets. This risk can be covered by a good insurance. As explained in a previous post, in order to prevent the spread of fire, NGK improved the design, the safety measures and the facilities organisation. When the next fire will take place, it is likely that the fire would be contained to the failed module or to a few, but the rest of the plant would be saved.

Prediction

Please do not misunderstand us. When we write “when the next fire will take place”, we are not pessimistic, but realistic. Fire incidents will occur, for sure. The risk zero does not exist. NGK did understand that, and reacted accordingly by concentrating their efforts on fire spread prevention. A clever move.

Now that NGK’s NAS batteries are back in business, it is time to turn the page and look at the future. It is the last time we mention the fire incident,… until the next one (we hope as late as possible).

Gauthier Dupont
Dupont Energy Consulting GmbH

NAS Battery Storage Systems List (update Sept. 2012)

Dupont Energy Consulting GmbH is happy to share with you the comprehensive list of facilities and projects of NAS battery storage systems in the world (see table below). We hope you will find the info interesting.

If you use it in any of your document, report, web site, etc., please reference the current page and mention the name of our company “Dupont Energy Consulting GmbH”. Thank you for your understanding and for respecting our work.

Do not hesitate to put in comment at the bottom of the current page any additional information you may have (on listed projects or projects not in the list). Upon verification, we will accordingly update the list.

We take the opportunity to make a call. We would like to compile an inventory of other types of large-scale batteries installed around the world (1 MW and above). It would be nice if you could send us information or post it in comment below. When enough data will be collected, the list will be shared on the same blog and on LinkedIn.

Gauthier Dupont
Dupont Energy Consulting GmbH

NAS Batteries back in the race soon ?

The biggest battery storage system in the world…

Tohoku Electric Power Co. Inc. set up a sodium sulfur (NAS) storage system at its Noshiro fossil-fuel-burning power plant. The system comprises forty 2 MW NaS batteries from NGK Insulators Ltd. able to continuously supply 80 MW for six hours. When it will be operational, it will be the biggest battery storage system in the world.

The system aims to prevent blackout in summer, thanks to load leveling (the batteries are charged during the night when the load is low and discharged in the afternoon during peak load hours). Tohoku EPCo is indeed unable to supply enough power because of the damage caused by the earthquake of March 11, 2011 (the one with the tsunami and Fukushima nuclear disaster).

…soon

It was expected to be running in January 2012, but because of the fire incident that occurred on September 21, 2011, the commissioning is postponed to April.

This announcement looks innocent, but it tells us that it seems that NGK is close to solve the problems raised by the fire incident.

Gauthier Dupont
Dupont Energy Consulting GmbH