225 kV interconnection between Mali and Ivory Coast : done !

A bit of history

Segou switchgearOn November 11, 2012, the high voltage power systems of Mali and Ivory Coast were connected for the first time. The new 225 kV overhead lines connection between Ferkéssédougou in the North of Ivory Coast and Ségou in Mali, via Sikasso and Koutiala, was put in operation. Not only the two countries are now interconnected in a single power system, but also Senegal, Mauritania, Burkina Faso, Ghana, Togo, Benin, Nigeria and Niger.

Ferke-SegouThe 520 km of new lines, that costed EUR 125 mio, were indeed the missing link between the 225 kV OMVS system and the 330 kV coastal backbone network from Nigeria to Ghana. The two networks, joined together in one, now constitute one of biggest power system in Africa, stretching over 3,000 km from Mauritania to Nigeria, as promoted by the WAPP (West African Power Pool) since decades.

The OMVS (Organisation pour la mise en valeur du fleuve Sénégal, in French) is the Senegal River Basin Development Authority. It was established in 1972 by the governments of Guinea, Mali, Mauritania, and Senegal.

Personal emotion

I am personally happy that the line is finally in operation. I remember my first power system planning study, back in 1997. It was precisely the feasibility study for the interconnection between Mali and Ivory Coast, performed by Lahmeyer Int. The interconnection was already defined in a regional master plan performed in the eighties.

SLD Mali Ivory CoastFor ten years, there had been no significant progress. Finally, in 2007, I had again to revisit the study. India came to help the two countries to finance the project and the feasibility study had to be updated, again by Lahmeyer Int. The lines were then built accordingly to the detailed design prepared in the study. Now, they are online. It is always a great feeling for a planner to see that what he recommended years ago is finally built.

The construction wasn’t easy, taking into account the political uncertainties and security issues in both countries. I would like to pay respect to the engineers and workers who built the line in extremely tough conditions.

A smart move

Building overhead lines is not especially what one understand in the term “Smart Grid”. But taking into account the lack of high voltage network in Africa, the investment is really smart. Let’s continue to interconnect countries in West Africa. The next interconnection could be Ghana-Burkina Faso-Mali (Bolgatanga-Bobo Dioulasso-Sikasso – 600 km) or Guinea-Mali (N’Nzérékoré-Fomi-Fomi-Bamako – 920 km).